SEALR Video Collection
A big milestone has been made to the SEALR scheme this week with blacktop going down on Lower Road roundabout and a new entrance to the offices constructed to assist with the next stage of phasing. The surfacing was laid by Galliford Try’s in house team and the whole operation went brilliantly, well done to all!
Video taken 14/02/25
The site has had made huge changes since the last full fly through. 2 rigs are installing concrete collumns to PH1 East, Major earthorks to the West with 90+ lorry movements per day. Lower Road’s civils are now complete. Phase 2 road box is almost all in, Western Roundabouts civils are very nearly complete. There’s lots to view in this one!
Video taken 05/02/25
First Railway Possession
The sheet piling commences in preparation the piling platform for the East Pier over a 50 hour possession of the railway line. The first possession works for the SEALR scheme
14/12/24
SEALR finally has a site offices!
28/06/24
In celebration of works commencing for Phase 2, we have produced a site fly through from the West end of Phase 2 all the way through to Wendover road
Video taken 15/05/24